Coal Seam Gas Central Processing Plant FEED Study
Key Capabilities
Front End Engineering
Cost Estimation and Analysis
Overview
Vecta conducted a FEED study for a new coal seam gas 80 TJ/d central processing plant in the Surat Basin Queensland. Part of this FEED study would comprise a 10% cost estimate for the detailed design, procurement, construction and commissioning phases of project delivery.
Scope
The scope included the following:
Front end engineering design. This included:
Development of drawings and documents in the Process, Mechanical, Civil, Electrical, Instrumentation & Controls disciplines;
Development of detailed 2D layout plans for the plant;
Scope preparation for detailed design and construction;
Preparation of vendor packages including technical specifications and datasheets for market pricing of major equipment items.
Project management including schedule, budget and technical queries;
+/- 10% cost estimate for detailed design, procurement, construction and commissioning. This included performing a Monte Carlo analysis to quantitatively analyse project risks;
Level 1 schedule
Challenges
The Client’s request was for the FEED and cost estimate to be executed over the Christmas period with an aggressive schedule. The deadline was fixed as the client required the information to present a proposal to the owners of the coal seam gas field in competition with other companies.
Lack of specific design information.
The client had an expectation of a Capex $/TJ of gas processed. During the course of the work the design and equipment specifications were challenged based on experience and modified to achieve the Capex expectation.
Delays in vendor pricing due to the Christmas period holidays.
Solutions
Vecta’s design team consisted of engineers who possessed extensive coal seam gas experience and with design of similar central processing plants. The team was involved in coal seam gas projects since the inception of the industry. The combined knowledge and experience of the team was critical to addressing gaps that were caused by a lack of design information.
Without the team’s experience the work could not have been completed in the aggressive schedule required.
Outcomes
The FEED phase of the project was completed on time and within budget.
The Client was pleased with the design proposed as well as the +/-10% cost estimate produced.